Three Clocks: Lease Terms, Refresh Rights and Delay Remedies

A data center lease runs 15 years or more, a GPU capacity contract three to five, and the GPUs inside it are superseded at least once before the contract ends. The lease terms decide who absorbs the gap.

By KloudXNov 20269 min readResearch as of Nov 2026

A wall covered with many clocks showing different times

"Pre-leasing has really turned the lease into a construction contract with a lease attached." That is how Peter Bergan, a partner at law firm Vinson & Elkins, described AI data center leases in October. Tenants are "signing leases two to three years ahead of when projects are actually up and running."

A lease signed for a building that doesn't exist yet is one clock. The GPU contract that fills it is a second, running on a different schedule. The GPUs themselves are a third, and they age fastest. GPU lease terms, and the data center leases around them, decide what happens when those clocks drift apart.

Three clocks, one deal

The building: 15 years and up, starting late. Data center leases are long. A form lease filed with the SEC by a Blackstone data center trust, BXDC, notes that the trust generally targets leases with "initial terms of at least 15 years." In that form, the lease begins at "the later of" the date a phase is delivered or a completion deadline. Bergan describes tenants pushing further, so that rent starts only once "all of the contracted power capacity is fully energized and fully commissioned." In his words, "Perhaps power is the product in the data center lease."

The compute contract: three to five years. GPU capacity contracts run much shorter. In a guide to GPU-as-a-service contracts, Chief Negotiators, a contract advisory firm, explains that offtakers, the customers committed to buy the capacity, sign for three to five years for a reason: "beyond five years you are underwriting a GPU generation you cannot forecast, and below three the provider cannot finance the capacity." One large example is IREN's contract with Microsoft: about $9.7 billion of total contract value over an average five-year term, with 20% of each delivery's value paid up front, according to an analysis by AI Infra Credit drawn from IREN's filings.

The GPUs: superseded before the contract ends. The hardware ages fastest. In a comparison of hyperscaler and neocloud contracts, Chief Negotiators notes that a three-year commitment signed on today's newest GPU "will outlive at least one successor." A five-year term can outlive more than one. That successor is close: Chief Negotiators notes that Nvidia's Vera Rubin platform is already reaching production supply. Rent, Lease or Own covers what such capacity costs.

What that hardware is worth at the end is uncertain. A distress framework from StackedAI models GPU residual value at about 15% of cost after a five-year term, while American Compute's server pricing model assumes 41% after three years. The two cover different time spans and neither is a market price, but any long contract quietly depends on an assumption like them. The wider cost picture is in Cost per Useful GPU-Hour.

Where the clocks collide

The trouble starts when the clocks are stacked on top of each other. StackedAI's framework flags two warning signs for GPU cloud providers: a colocation lease that "outlives customer contracts," and debt that "matures after it ages out," meaning after the GPUs it financed have lost most of their value. In a failure, it warns, the result can be "a building full of orphaned hardware."

Lenders look at the same contracts from the other side. AI Infra Credit sums up its test in three sentences: "A contract is not cash. A lien is not recovery value. A facility rating is not a customer rating." In plain terms, a signed contract, a claim on equipment and a good credit score for the project are not the same as reliable payments from a strong customer. A contract becomes financeable, it says, only after "delivery, acceptance, minimum-payment obligations, cash control, and replacement mechanics are demonstrable." The Compute Register makes the delivery point bluntly: "a take-or-pay contract with a hyperscaler is worthless if the facility never gets energized on schedule."

What makes a contract bankable for a provider, a fixed minimum payment, an early commitment, a long term, is usually what puts the risk on the buyer. The terms below are how buyers take some of it back.

The terms that rebalance the clocks

Most of these come from the same sources, and each answers a specific way the clocks can drift apart.

TermWhat it protects againstWhat it looks like
Rent starts at energizationPaying for a building before its power is liveRent begins when contracted power is "fully energized and fully commissioned" (Vinson & Elkins)
A delay ladder with a real top rungA site that slips for monthsA grace period of "60, 90 days," then "day-for-day or multiple-day rent abatement," meaning rent reductions for each day of delay, then a right to terminate at an outside date, a final deadline after which the tenant can walk away (Vinson & Elkins)
Acceptance before billingPaying for GPUs that don't yet work as a clusterBilling starts only after the cluster passes agreed burn-in and performance tests; burn-in means running the system hard to expose weak parts. AI Infra Credit lists "delivery, acceptance" among the conditions before a contract counts as financeable cash flow
A refresh rightBeing locked into an aging GPU generationA right to move to the next GPU generation at a price set in advance; Chief Negotiators lists "hardware generation and refresh rights" as negotiable
Assignment and exitCapacity that is no longer neededRights to transfer the contract or leave it early; Chief Negotiators lists "exit and assignment" among the terms GPU-focused clouds will negotiate

Two details deserve attention. First, delay remedies are usually capped. Bergan notes credits of "three months of rent, up to maybe one year's worth of rent," often described as the tenant's "sole and exclusive remedy" before termination, and the BXDC form includes the same structure as an optional clause. The cap and the outside date should match the real cost of a delay to the buyer, not a standard figure.

Second, a refresh right can be worth more than a lower rate. Chief Negotiators argues that "a right to migrate to the next generation at a defined price is usually worth more than a further two points of discount." Acceptance testing matters for similar reasons, since the tests catch real faults, as NVL72 Lessons describes.

The cancellation clock

One more clock sits inside every contract: how quickly each side can leave. A very large example came in October. According to Yahoo Finance's report on Anthropic's IPO filing, the company could spend up to $120.5 billion on computing capacity with SpaceX through 2029, rising to about $3.1 billion a month at full delivery. After initial periods ending in January and March 2027, "either Anthropic or SpaceX can terminate on 90 days' notice."

For the buyer, a 90-day exit on a multi-year commitment is valuable flexibility. For the provider, and for anyone lending against that revenue, it is the opposite. The same clause looks very different depending on which side of it you sit on. So before signing, it is worth asking three questions about cancellation: who can end the contract, after how long, and at what cost, on both sides.

Dates before signatures

A lease's delay remedies are easier to negotiate with an independent view of the site's real schedule. Request an assessment before the terms are final.