Model My Cluster.

Start with the GPUs you need. See the power, racks, cooling, and capacity behind them.

Estimated IT load

1.28 MW

Estimated facility requirement

1.51 MW

Capacity tier

AI Pod

Planning units

128 8-GPU nodes

Estimated racks

32

Rack density

40 kW / rack

Cooling guidance

Air or liquid; liquid preferred at scale

Matching capacity

0 published sites

No single published site covers this today. Capacity changes weekly - request an assessment.

Planning baseline: 45 days from site and hardware readiness.

12-month base reference: $2.15 per GPU-hour (range $1.75–$2.65), updated Oct 15, 2026. Illustrative underwriting range, not a quote.

Displayed rates and ranges are illustrative 12-month underwriting ranges, not verified provider quotes.

Planning model only. Results are estimates, not engineering guarantees. All pricing, equipment availability, data center capacity, power availability, and deployment timelines are subject to availability. Estimates are based on weekly supply and deployment forecasts and may change daily due to hardware allocation, facility capacity, utility availability, logistics, network readiness, and other market conditions. Final pricing and delivery dates are confirmed only in an executed customer agreement.