Proof of Power: How to Tell a Real Megawatt From a Promised One
A landlord says the site has 20 MW. This guide to data center power verification explains what a will-serve letter really proves, why a nearby substation isn't capacity, and the six documents that separate real power from a promise.
By KloudXNov 20269 min readResearch as of Nov 2026
"Powered" may be the most valuable word in a data center listing right now. Space with power is scarce, so a powered shell commands a premium. Yet the word itself guarantees nothing. It can describe a building with live capacity and a tested handover. It can also describe a building next to a busy substation, with a one-page utility letter on file that promises no megawatts and no date.
Too often the difference surfaces only after the lease is signed, when a tenant learns that the upgrade it needs will take years. "Powered" is a label, not a power date. Data center power verification means checking the documents behind the label: what the utility has actually agreed to deliver, at what voltage, from which substation, by when, and who pays for the work to get there.
Microsoft walked away from a site the grid couldn't serve
A 50 MW project in Essex, England, lost its anchor customer over exactly this gap. In October, The Register reported that Microsoft had ended its anchor deal for Nscale's site at Loughton. The site had been pitched with 23,040 Nvidia GB300 GPUs and first chips in early 2027, but reports said grid power might not arrive until the early to mid 2030s.
The local network operator explained the gap in one sentence. Many data centers, its spokesperson said, "can connect to our distribution network" but "are awaiting works on the national transmission network which we do not own."
A site can have a working connection to the local network and still be years away from the capacity an AI hall needs, because the bottleneck sits further up the grid. The building was real, the plan was real and the customer was real. The power date wasn't.
What a will-serve letter proves, and what it doesn't
The document landlords show most often is a utility will-serve letter. It sounds like a commitment. Usually it isn't.
A practical guide from Build, published in November, lays out what these letters typically confirm: that the site is in the utility's territory and that the utility is willing to serve it. On the questions that matter to a buyer, the answers are thin. Does the letter say when power will be energized or who pays for upgrades? "Rarely." Does it reserve capacity? "Usually no."
Build's rule of thumb is blunt: with a letter and no study, "Treat the site as unvalidated for power," and "Underwrite to the agreement, not the letter."
In plain terms, there is a ladder of proof:
- A will-serve letter. The utility is willing in principle. No megawatts or date are guaranteed.
- A load study. The utility has modeled the load on its network and identified what upgrades it would need.
- A signed facilities or electric service agreement. Megawatts, milestones, deposits, cost allocation and a ramp schedule, in a contract.
- Energized capacity. Power is live at the building, tested and ready to hand over.
A "powered" listing may sit only on the first rung. A buyer paying powered-shell rent should know which rung they are paying for.
A substation next door isn't spare capacity
Proximity is the second common trap. A substation down the road looks like power on tap. Often it means someone else already asked for that capacity.
Even when there is room in principle, the equipment is the long pole. Recruiter Spencer Ogden, in its review of grid connection waits, reports that lead times for substation transformers now exceed 160 weeks, more than three years. You can build a data hall in less time than it takes to receive the transformer that feeds it.
Queues add to the wait. Enverus found that projects in the utility interconnection queue that reached first power in 2025 spent over 2,100 days, almost six years on average, between entering the queue and operating, and that only about 10% of queued capacity gets built. That is why a realistic energization date is so hard to pin down.
The interconnection queue is being cleaned out
Utilities and regulators have noticed how many requests in the queue are speculative, and they are starting to sort real projects from placeholders. That is good for serious buyers, but it changes what "in the queue" means.
Texas shows it most clearly. ERCOT's Batch Zero update sorted large-load requests from 735 projects, roughly 494 GW in total. It conditionally kept 66.4 GW as base load and excluded 302.2 GW. ERCOT has also paused energizing new data centers of 75 MW or more since Aug 3, with verification reports due on Dec 10, 2026. And under a new Texas rule effective Oct 8, new ERCOT large loads of 75 MW or more must post $50,000 per MW in security just to be studied, according to GridTilt. For an illustrative 100 MW request, that is $5 million up front.
In the PJM region, FERC accepted a new registry for loads of 50 MW or more on Oct 9, effective Oct 12. It collects each project's location, ramp schedule, peak demand and backup generation.
A landlord with a genuine place in line has paid for it and has paperwork to show. If the answer to "which study is this load in?" is vague, the place in line probably isn't real.
Behind-the-meter power is faster, but mostly still on paper
When the grid is years away, many developers turn to behind-the-meter power: generation on site, such as gas engines, turbines or fuel cells, often as a bridge until the grid connection arrives.
It can be fast. Bloom Energy's chief executive said on an earnings call that the company delivered power to Oracle's Utah site in less than two months, as Reuters reported. Modular gas engines and fuel cells can reach commercial operation in 18 to 24 months, compared with up to 80 months for large combined-cycle plants, according to an Enverus forecast reported by Power Engineering.
But announced on-site power is very different from running on-site power. Cleanview counted about 90 GW of behind-the-meter generation announced across 59 US campuses, with only about 2 GW operating in mid-2026. It also names the slips: a blocked gas pipeline at one site, and an air permit still pending for a 400 MW on-site plant at another.
Skipping the grid doesn't skip the permits. On-site power still needs fuel, an air permit and neighbors who accept it. It also needs the right design: GE Vernova notes that AI training loads swing too fast for a turbine to follow directly, so bridge power needs batteries and a medium voltage UPS in between.
So if a landlord's power story depends on on-site generation, the same question applies: is it permitted, fueled and contracted, or only announced?
Six documents to ask for before signing
Here is a simple check any buyer can run before signing for a "powered" site. Ask the landlord or developer for these six documents:
- The utility document behind the megawatts. A letter or agreement that names the MW, the voltage and the substation or feeder that serves the site.
- The load study. Its status, its date and a copy, including the upgrades it identified.
- The signed service agreement. A facilities or electric service agreement with milestones, deposits and a ramp schedule. This is the document that commits a date.
- Who pays for upgrades. The cost allocation for substation, line and transformer work, and what happens if those costs rise.
- Expiry and assignability. When the commitment lapses, and whether it transfers to a tenant or a new owner.
- The handover schedule. What is energized today versus planned, with the building boundary, electrical boundary and remaining fit-out named. A guide from Percepture lists "Power nearby means power committed" as the first assumption to challenge and recommends asking for exactly this schedule.
Where possible, confirm the key facts directly with the utility. And if the site relies on on-site generation, add three more: the air permit, the fuel supply contract and the plan for when the grid connection arrives.
How to read the answers
The six documents rarely all exist. That's normal. What matters is pricing the site for what it really has.
- Signed agreement, dated milestones, upgrades funded: the power is real. Check the energization date against your own deployment plan, and remember that "power at the site" still has to become critical IT capacity your racks can use.
- Load study done, no agreement yet: the power is likely but not committed. Ask what is blocking the agreement and how long it usually takes with this utility.
- Letter only: the site is unvalidated for power. It may still be a good site, but the rent, the deal terms and your timeline should reflect that.
- "There's a substation right there": treat it as no information at all until the utility confirms capacity.
A will-serve letter, a nearby substation and an announced on-site plant all sound like megawatts. None of them is a power date. The paper shows where a site really stands, and the rent should reflect it.
Checking a site's power?
To go through the power documents for a specific site, request an assessment.
Sources
Figures are as reported by each source at the time of writing. Research as of Nov 2026.
- The Register, on Microsoft ending its Loughton anchor deal (Oct 19, 2026)
- Build, on what a utility will-serve letter proves (Nov 2026)
- Spencer Ogden, on grid connection waits and transformer lead times
- Enverus, on time to power for data centers (Apr 2026)
- ERCOT, Batch Zero update to the board (Sep 2026)
- GridTilt, on ERCOT's energization pause and the new security rule
- FERC, order on PJM's large load registry (Oct 9, 2026)
- Reuters, on fuel cells for AI data centers
- Power Engineering, on Enverus' behind-the-meter forecast
- Cleanview, behind-the-meter data center report
- GE Vernova, on bridging power for AI campuses
- Percepture, on powered shell handover and diligence (Oct 23, 2026)
Image credits
Cover photo: American Public Power Association on Unsplash
More from the blog
Power and Sites
Build, Colo or Land: Choose by Power Date, Not Price
Nov 2026
Power and Sites
Gross MW vs IT MW: How Much Compute Fits in a 20 MW Building
Nov 2026
Buyers and Strategy
APIs, Private Models or Sovereign AI: The 2027 to 2030 Outlook
Nov 2026