Is Your Building Ready for 140 kW and 220 kW Racks?
GB300 racks draw up to 142 kW and Vera Rubin racks about 220 kW, all of it carried away by liquid. Liquid cooling readiness means a path for that heat from the rack to the roof, the equipment to build it, and a clear answer on who pays.
By KloudXNov 20269 min readResearch as of Nov 2026
Nvidia's newest racks are cooled with water hotter than a hot tub. In a June post, the company described coolant entering the rack at 45°C (113°F) and leaving the chips at roughly 55°C, and said its Rubin generation is the first to cool "every chip, every networking component" by liquid, "with no fans anywhere in the system," according to Nvidia.
Warm water sounds like a poor way to cool anything. It works because liquid carries heat far better than air, and it changes what a building needs. With GB300 or Vera Rubin racks, liquid cooling is no longer optional. What varies from building to building is whether it can move that much heat, at that temperature, from the rack all the way to the outside air.
The clearest way to judge that is to follow the heat.
At the rack: 140 kW today, about 220 kW next
Vertiv rates its factory-built GB300 NVL72 rack at up to 142 kW. For Vera Rubin, one analyst model reported by Investing.com uses a rack rating of 220 kW, all of it in a single rack.
Inside the rack, the work is done by cold plates: metal blocks fixed to each chip, with coolant running through them. This is what direct-to-chip liquid cooling means. The servers arrive with the cold plates and manifolds built in. What they need from the building is a supply of coolant at the right temperature, pressure and flow, and somewhere to send the heat.
Density also changes how much a building can hold. As the illustrative arithmetic in the guide to gross MW vs IT MW shows, at about 140 kW and 220 kW per rack, the same 14.3 MW of IT holds about 102 GB300 racks but only about 64 Vera Rubin racks. A hall can be "liquid-ready" for one generation and short of power or cooling for the next.
The CDU: where the building meets the rack
Between the rack and the building sits a coolant distribution unit, or CDU. It keeps the rack's coolant in its own clean, closed loop, and passes the heat across a heat exchanger to the building's water. Nvidia describes coolant flowing from the CDU to the servers "in a closed-loop" system that is "filled once."
CDUs are sized in megawatts, and they set the shape of a room. Supermicro's Vera Rubin deployments use in-row CDUs "rated at 1.8MW per CDU, deployed with N+1 redundancy," meaning one more unit than the load needs, so a single failure doesn't stop cooling. As illustrative arithmetic, 1.8 MW covers about eight racks at 220 kW, so a row of Vera Rubin racks needs several CDUs, plus the spare, plus the floor space, piping and power to run them.
This is also where most of the risk sits. Every rack connection is a joint that can leak, and every loop has to be flushed, filled and pressure tested before servers are connected. That commissioning step, described in Delivered Isn't Live, is one of the places where AI deployments lose months.
The facility water loop and the trip outside
Behind the CDUs runs the facility water loop: the building's own piping that carries heat away from the data hall. In an air-cooled building it may not exist at all, or exist only to serve air handlers. In a liquid-ready building it reaches every row, sized for the full IT load.
At the end of that loop, the heat has to leave the building. Traditionally that means chillers and cooling towers. This is where the warm water pays off. Nvidia says 45°C coolant "can enable chiller-less operation with dry coolers" in favorable climates (dry coolers are large fan-driven radiators that shed heat to the outside air without evaporating water), cutting cooling-tower water use, which it puts at roughly 2.6 million gallons per megawatt per year, to near zero. The same post adds the caveat that matters for site selection: "A data center in the Scottish Highlands and one in Phoenix, Arizona, face very different realities." In a hot climate, chillers still run on the hottest days.
So the heat-rejection plan depends on where the building is, and the design water temperature has to match the racks it will serve. A loop designed years ago for cold water and air handlers is a different system from one built for 45°C supply.
The parts with the longest wait
Even a well-designed plan needs equipment, and cooling gear has become a long-lead item. At an industry event in October, panelists told Bisnow that chillers and other cooling components routinely carry lead times of 12 to 18 months.
Demand explains why. Vertiv, one of the largest makers of data center power and cooling equipment, reported third-quarter net sales up 61% from a year earlier and organic orders up more than 100%.
The practical effect is simple: a building whose chillers or other heat-rejection equipment are not yet ordered may be a year or more from being liquid-ready, however good the drawings look. Electrical gear adds its own wait. A guide from broker Data Center Scouts, citing Cushman & Wakefield, lists 68 to 113 weeks for pad-mounted transformers and 60 to 100 weeks for generators.
Retrofitting an air-cooled hall
Many buildings on the market were designed for air. Converting one is possible, and it can be cheaper than building new, but it is rarely as simple as adding pipes.
A sponsored analysis by STL Partners puts a liquid cooling retrofit at around $2 million per MW, compared with upwards of $11 million per MW for new greenfield liquid-cooled capacity, by its estimate. (Other estimates for new AI-ready buildings run higher.) It also lists the costs that don't show up in that number: "downtime risk, lost tenancy revenues, workload migration."
There are halfway steps. Rear-door heat exchangers cool the air leaving air-cooled servers with a liquid coil on the back of the rack. Liquid-to-air sidecar CDUs serve liquid-cooled servers in a building with no suitable facility water, by dumping the heat back into the room's air. Supermicro, for example, sells both. They suit modest densities and transitional rooms. They are not a substitute for a facility loop at 140 kW or 220 kW per rack across a whole hall.
Factory-built pods don't remove the requirement either. Nvidia notes in its DSX POD FAQ that even its containerized, factory-tested racks need a prepared site with connections to power, facility water, cooling and the network.
Who pays for the inside of the building
A common and costly assumption is that a landlord's building includes the cooling. In a powered shell, a building leased with power but without the internal systems, it usually doesn't. Data Center Scouts, citing the CRE Finance Council, puts mechanical, electrical and plumbing systems at 60% to 70% of development cost, with the shell at 20% to 30% based on figures from the ratings agency KBRA. Its summary for tenants: "In a powered shell, most of that 60 to 70% is yours."
The filings show the scale. Applied Digital reported $183.5 million of revenue from tenant fit-out services in the quarter ended Aug 31, 2026, next to $65.8 million of base rent. At Cipher Digital's Barber Lake site, the cost rose from the $10.4 million per IT megawatt the project was financed at to $13 million, driven by tenant change orders and higher construction costs. For the higher construction costs, Cipher says it is "sharing these costs equally with our tenant and recovering our tenant share through rentalization," that is, through higher rent. For future leases it plans to advance design sets "to between 30-60% complete ahead of lease execution" to avoid repeats.
Both points matter to a buyer. The cooling plant is a large share of the cost, and design changes after signing are what drive overruns. Settling the rack density, coolant temperature and CDU layout before the lease is signed is the cheapest protection available.
What "liquid-ready" should mean on paper
Following the heat backward gives a simple way to test the claim. Each step has something that can be shown, not just described:
| Step | What to see | Why it matters |
|---|---|---|
| Rack | The target rack model and its rated kW, matched to the floor's power per rack | A room sized for 140 kW racks may not run 220 kW racks |
| CDU | CDU model, capacity, count and redundancy per row; delivery dates if not installed | Sets how many racks each row can run, and when |
| Facility loop | Design supply temperature and flow, and whether the loop reaches every row today | A loop built for air handlers is not a loop for direct-to-chip |
| Heat rejection | Chillers or dry coolers, their capacity at the site's hottest conditions, and order or delivery status | 12 to 18 month lead times make "on order" a schedule question |
| Commissioning | A date for flushing, filling and pressure testing the loop | The step between a finished hall and running racks |
| Scope | The work letter, the lease document that lists who builds and pays for what | Most of the cost sits here |
A building that can show all six is liquid-ready. One that can show the first two is liquid-capable, which may still be a fine choice with the right price, schedule and scope split.
Cooling, checked before the lease
Comparing a building's cooling with the racks it will have to run is part of a KloudX site assessment.
Sources
Figures are as reported by each source at the time of writing. Research as of Nov 2026.
- Nvidia, on 45°C liquid cooling for AI factories (Jun 21, 2026)
- Vertiv, SmartIT for NVIDIA GB300 NVL72
- Investing.com, on the cost of deploying Vera Rubin infrastructure
- Supermicro, Vera Rubin NVL72 shipping release (Sep 23, 2026)
- Bisnow, on data center supply chains (Oct 25, 2026)
- Vertiv, third quarter 2026 results (Oct 28, 2026)
- Data Center Scouts, on powered shell costs and lead times (updated Nov 5, 2026)
- STL Partners, on the economics of liquid cooling retrofits
- Nvidia, DSX POD product FAQ
- Applied Digital, fiscal first quarter 2027 results (Oct 7, 2026)
- Cipher Digital, third quarter 2026 earnings call (Nov 2, 2026)
Image credits
Cover photo: Ricardo Gomez Angel on Unsplash
More from the blog
Facility Readiness
The Network Inside an AI Factory: Optics, Cabling and Placement
Nov 2026
Buyers and Strategy
APIs, Private Models or Sovereign AI: The 2027 to 2030 Outlook
Nov 2026
Buyers and Strategy
Enterprise GPU Buyers: Who Buys and Who Decides
Nov 2026